Washington Street's Blue Line Construction Schedule, Block by Block, for Buyers

November 19, 2026

West Washington Street finally got its bridge over Little Eagle Creek back in 2025, after nearly two years of delays. Then, as Mirror Indy reported in late September, Blue Line construction arrived on that part of the street in early September 2026. Traffic there now runs east only, and the next blocks are scheduled to be torn up for new storm sewers.

If you're comparing homes along Washington Street, that account matters more than any forecast about what the Blue Line will do to values. IndyGo says the 24-mile line will run from Cumberland to Indianapolis International Airport and open for service in 2028. The construction comes first, and it doesn't hit the whole corridor at once. IndyGo split the work into 12 areas and expects impacts from 2025 through 2028. So two houses with the same Washington Street address can sit two years apart in that cycle. In a county with far more homes for sale than usual, a buyer's timing and negotiating room depend on which stretch a house is on.

Where each stretch stands as of late November

IndyGo keeps a segment-by-segment construction page and updated most of it in October and November 2026. This table summarizes it from west to east.

Stretch of Washington Street Status on IndyGo's construction page
Holt Road to Rockville Road AT&T and Citizens Energy Group are relocating utilities; Blue Line work is scheduled for late 2026 through 2028
Rockville Road to Belmont Avenue Westbound closed between North Tibbs and Belmont avenues for sewer work; one eastbound lane open
Belmont Avenue to White River Bridge One lane each way; Harding Street and Belmont Avenue stations under construction; detention facility being built under Indianola Park
White River Bridge to Alabama Street Inside lanes closed for the Zoo and White River Park stations; up to two lanes each way open
Alabama Street to Southeastern Avenue Inside lanes closed near Park Avenue and Southeastern Avenue for station work
Southeastern Avenue to State Avenue November update set mid-November for one lane each way to reopen and Oriental Station work to start in the center of the street
State Avenue to Emerson Avenue Eastbound closed for sewer work; detention facility being built at Willard Park; one lane each way near Pleasant Run Parkway
Emerson Avenue to Ritter Avenue Eastbound closure scheduled on or after Dec. 1 for about 160 days
Ritter Avenue to Arlington Avenue Scheduled for 2027
Arlington Avenue to Shadeland Avenue Scheduled for late 2027 through mid-2028
Shadeland Avenue to Woodlark Drive Station, sidewalk and curb ramp work under way for Sadlier Drive, Franklin Road, Fenton Avenue, Post Road, Cherry Tree, Mitthoefer Road and Washington Pointe stations

The west end needs one note. A 2024 IBJ report said the Blue Line will turn off Washington Street at Holt Road and take I-70 to the airport. That means planning activity farther west along Washington is not on the line's path.

The west side is in its heaviest stretch now

On the near west side, around Hawthorne and the blocks toward Belmont, buyers are looking at the hardest part of the work. Mirror Indy reported that the work between Belmont and Rockville was expected to last through March 2027, and that the stretch from Rockville to Holt would continue through 2028. For a buyer, that changes what a showing tells you. A house near the Harding Street station site this winter shows you the corridor at its noisiest and most detoured. That's the version of the street a seller is competing against, and it should show up in how long a listing sits and how much room there is to negotiate.

West of Rockville, the timing flips. Utility crews are working there now, and the main Blue Line construction hasn't arrived yet. If you buy there this winter, you'd likely own the house through the construction rather than buying after it.

The Near Eastside is moving from pipes to stations

Between Southeastern and Emerson, the work is changing from what's underground to what you'll see on the street. IndyGo's November update set mid-November for two-way traffic to return between Southeastern and State avenues, with one lane each way, and for construction of Oriental Station to begin in the center of Washington Street. The underground storm water detention facility at Willard Park is being built inside the park, and IndyGo doesn't expect it to affect traffic. The park stays open with some activities restricted.

Some new buildings along this stretch were already open before the construction started. TWG's Line Lofts at 1145 E. Washington St. opened in 2021 with 63 affordable two-bedroom senior apartments, and the developer described it as next to the future Blue Line corridor. Next door is The Assembly, where Ash + Elm Cider Co. opened a cidery and restaurant. On these blocks, the apartments and the cidery are already there, while the station work is just getting started.

Irvington's longest closure is scheduled for this winter

Buyers looking at Irvington have the most specific dates to plan around. The closure on the north side of the Washington Street and Emerson Avenue intersection has already run past its original 12-day estimate. On or after Dec. 1, Washington Street is scheduled to close to eastbound traffic between Emerson and Ritter avenues for storm sewer work, with one westbound lane kept open. IndyGo expects that work to take about 160 days, which runs into spring 2027. After that, the work moves east: Ritter to Arlington in 2027, then Arlington to Shadeland from late 2027 into mid-2028. IndyGo held an Irvington community meeting on Sept. 3, 2026, and posted a recording on its construction page, which is worth watching before you write an offer. If Irvington's historic district is part of your search, our earlier post on what the Certificate of Appropriateness means for Irvington buyers covers a separate piece of buying there.

So a house east of Ritter could be through a winter of eastbound detours on its stretch before the construction crews ever reach its own block.

Why the schedule matters more in this market

Construction alone doesn't give a buyer much room. A wide choice of homes does, and Marion County has one right now. Indiana REALTORS' report for October 2026 shows an average of 3,609 homes on the market each day, 20% more than in October 2025. The report's expected range for the month was 2,547 to 2,815. Months of supply reached 3.7 in October 2026, at the top of the expected range. Homes that went under contract in October took a median of 35 days, 35% longer than a year earlier, though that's still a bit faster than the 37 to 41 days the report expected for the season.

Prices have held up better than the supply numbers. The countywide median sale price in October 2026 was $240,000, down 3% from October 2025 and within the report's expected range. Homes sold in October for 94.3% of list price, also within the expected range of 93.5% to 95.4%.

Prices slipped a little over the year, while the supply of homes grew a lot, and buyers have more time to decide. On a stretch with lane closures, a buyer who walks away from one house has plenty of others to look at. These are countywide numbers, so they don't single out the Washington Street corridor.

Paying for the house as it stands today

The case for buying along the corridor usually rests on the 2028 payoff. IndyGo credits its bus rapid transit system with more than $1.2 billion in economic development. That figure covers the whole system and doesn't isolate any one line. The Red Line runs along College Avenue, and the Purple Line opened along 38th Street in October 2024. Neither line gives you a figure you can apply to one particular house on Washington Street.

So I'd suggest a different approach. Pay a price that makes sense for the house as it stands today, on a street that's under construction, and treat the finished line as a possible upside, not something to price in. In practice, that means a few things:

  • Find your block on IndyGo's construction page before the first showing, and note whether the main work is done, under way, or still ahead.
  • Visit at least once on a weekday morning. Mirror Indy's west-side reporting described crews starting at 7:30 a.m.
  • Drive the posted detour from the house to your work and back. The Emerson closure, for example, sends Washington Street traffic north on Sherman Drive and east on New York Street.
  • Ask how long the listing has been active, and compare that with the county's October median of 35 days.

Sellers along the corridor can use the same calendar. If your block's heavy work ends before a later stretch's begins, listing in that gap means buyers see a quieter street. A home valuation that accounts for where your block sits on the schedule is a good place to start.

A few questions buyers ask about the Blue Line

When does the Blue Line open? IndyGo's current project page lists 2028 for the start of service, from Cumberland to the airport.

Does the line run on Washington Street all the way to the airport? No. The 2024 IBJ report said the route leaves Washington Street at Holt Road and uses I-70 for the rest of the trip to the airport.

Which stretch has the most construction still ahead? On IndyGo's schedule, Arlington Avenue to Shadeland Avenue on the east side starts in late 2027 and runs into mid-2028. On the west end, Holt Road to Rockville Road is scheduled from late 2026 through 2028.

If one of your options is a house on Washington Street, send me the address and we can look at where that block falls on IndyGo's schedule together before you decide what to offer. You can learn more about how Andrew Prince works with buyers across Indianapolis, or reach me directly. Let's Connect.